Approval has been granted for the renewal of the Limited Operational Flexibility for an Environmental Compliance Approval (air & noise) No. 2192-8QWQCW for Enbridge Gas Inc. for facilities across the Province of Ontario.
This proposal is for the renewal to Permit to Take Water No. 2765-BZGLC9 for 1919427 Ontario Inc. Water will be taken from two wells, located in Milton, for campground and recreational water supply purposes.
Instrument type:
Changes to the site plan for a pit or quarry
ERO number
026-0294
Notice type
Instrument
Notice stage
Proposal
Proposal posted
Comment period
April 1, 2026 - May 1, 2026 (30 days) Open
Last updated
Béton Provincial Ltée seeks to authorize Licence 5761 to deepening the quarry floor from 44 meters above sea level (masl) to a new floor elevation of 18 masl and Licence 625349 to deepening the quarry floor from 35 masl to a new floor elevation of 18 masl.
February 18, 2026 - March 20, 2026 (30 days) Closed
Last updated
The Director of Exploration has made a decision on the exploration permit application PR-26-000028 to Graycliff Exploration Limited for early exploration activities. The decision is to issue the mineral exploration permit.
February 10, 2026 - March 12, 2026 (30 days) Closed
Last updated
The Director of Exploration has made a decision on the exploration permit application PR-000012 to GFG Resources for early exploration activities. The decision is to issue the mineral exploration.
December 8, 2025 - January 22, 2026 (45 days) Closed
Last updated
Approval is granted to operate a 2.35‑hectare facility in the City of Barrie, Ontario, for the receipt, storage, transfer, and processing of non‑hazardous waste, including dry excess soil, road sweepings, and liquid excess soil.
December 22, 2025 - February 5, 2026 (45 days) Closed
Last updated
We have issued an amended Environmental Compliance Approval with Limited Operational Flexibility (air & noise) to Linde Canada Inc., a liquid carbon dioxide manufacturing facility located at 566 Southdown Road in Mississauga, Ontario.
The proposed work program for the Methuen Township Marble Project would be a stripping and drilling bulk sampling program removing no more than 950 tonnes of material, keeping the project below the threshold of advanced exploration. The location of the bulk sampling is a near surface rock outcrop with light overburden, in a forested area.
November 3, 2025 - December 3, 2025 (30 days) Closed
Last updated
Permit to Take Water No. P-300-3382204449 has been issued to INVERARY GOLF & COUNTRY CLUB INC. for golf course irrigation and water supply purposes. Water will be taken from three drilled wells and four ponds: Clubhouse Well, Shop Well, Backup Well; and Ponds 1, 2, 3 and 4, in South Frontenac.
This notice is to inform the regulated community and the public that we are adopting updated approved air dispersion model versions under Ontario Regulation 419/05: Air Pollution – Local Air Quality. The updated model versions will take effect upon publishing of this notice.
February 29, 2024 - April 29, 2024 (60 days) Closed
Last updated
The Canadian Board for Harmonized Construction Codes is consulting on proposed changes for the 2025 National Construction Codes, some of which may affect the environment.
Please use the link to the National Public Review found below to submit your comments:
November 3, 2023 - December 18, 2023 (45 days) Closed
Last updated
The Canadian Board for Harmonized Construction Codes is consulting on proposed changes for the 2025 National Construction Codes, some of which may affect the environment. Working towards increased code harmonization, we encourage people to provide feedback as we consider the proposals for potential inclusion in the Ontario’s 2026/27 Building Code.
December 13, 2023 - January 27, 2024 (45 days) Closed
Last updated
The Ministry of Municipal Affairs and Housing will be enhancing its monitoring of certain housing development Minister's Zoning Orders that have made limited progress.
Instrument type:
Approval for a consent (subject to conditions) in an area where there is no official plan in place
ERO number
019-7610
Notice type
Instrument
Notice stage
ProposalUpdated
Proposal posted
Comment period
September 21, 2023 - October 21, 2023 (30 days) Closed
Last updated
The purpose of this application is to sever one new lot from the south part of PIN 31159-0231, approximately 22.2 hectares in size, for recreational purposes.
Instrument type:
Approval for a consent (subject to conditions) in an area where there is no official plan in place
ERO number
019-7611
Notice type
Instrument
Notice stage
ProposalUpdated
Proposal posted
Comment period
September 21, 2023 - October 21, 2023 (30 days) Closed
Last updated
The purpose of this application is to sever one new lot from the south part of PIN 31159-0231, approximately 13.3 hectares in size, for recreational purposes.
Instrument type:
Approval for a consent (subject to conditions) in an area where there is no official plan in place
ERO number
019-7612
Notice type
Instrument
Notice stage
ProposalUpdated
Proposal posted
Comment period
September 21, 2023 - October 21, 2023 (30 days) Closed
Last updated
The purpose of this application is to sever one new lot from the south part of PIN 31159-0231, approximately 12.7 hectares in size, for recreational purposes.
Instrument type:
Draft approval of a plan of subdivision in an area where there is no official plan in place
ERO number
019-6924
Notice type
Instrument
Notice stage
ProposalUpdated
Proposal posted
Comment period
May 3, 2023 - June 2, 2023 (30 days) Closed
Last updated
The Ministry of Municipal Affairs and Housing (MMAH) is seeking to make a decision on a plan of subdivision (58-T-208305) on Pine Point on Lac Des Mille Lac.
Instrument type:
Changes to the site plan for a pit or quarry
ERO number
026-0295
Notice type
Instrument
Notice stage
Proposal
Proposal posted
Comment period
March 31, 2026 - June 1, 2026 (62 days) Open
Last updated
Drain Bros. Excavating Limited seeks to extract below the water table in the east setbacks, which are adjacent to land also owned by Drain Bros. Excavating Limited. The amendment would allow for the existing pond to connect with the pond proposed through the adjacent expansion application.