February 16, 2024 - March 17, 2024 (30 days) Closed
Last updated
Permit to Take Water No. 6332-D3ZLKB was issued to Rogers Communication Inc. on May 8, 2024, to renew Permit to Take Water No. 70713-9DTKMJ for groundwater remediation purposes. Water will be taken from one remedial well system in the City of Brampton, Regional Municipality of Peel, Ontario for 10 years.
Instrument type:
Changes to the site plan for a pit or quarry
ERO number
019-6890
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
March 31, 2023 - May 1, 2023 (31 days) Closed
Last updated
Approval was granted for a site plan amendment to allow Marcel Brazeau Limited to amend several operational details on the site plan for Licence No. 4177, operating in the City of Ottawa.
February 9, 2024 - March 10, 2024 (30 days) Closed
Last updated
The Permit to Take Water P-300-1726597278 was issued to Mistral General Contracting Inc. on May 3, 2024. Water will be taken from two ponds for construction dewatering purposes, located in the City of Ottawa, Ontario.
The Permit to Take Water No. 3167-D4SN9K was issued to Lafarge Canada Inc. on May 3, 2024, to renew the permit 7580-9GQJUL. Water will be taken from one quarry sump for dewatering and aggregate washing purposes at the Nolan Quarry, located in Clarence-Rockland, United Counties of Prescott and Russell, Ontario.
October 4, 2023 - November 18, 2023 (45 days) Closed
Last updated
A new Environmental Compliance Approval (ECA) was issued to COM2 Computers and Technologies (Canada) ULC Operating as COM2 Recycling Solutions for a waste electrical and electronic equipment transfer and processing station. This Site is located at 1704 Meyerside Drive in Toronto, and is permitted to accept waste electrical and electronic equiment.
Instrument type:
Approval of a municipality’s official plan
ERO number
019-6503
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
February 17, 2023 - March 19, 2023 (30 days) Closed
Last updated
A decision was made on April 26th, 2024 to approve, with modifications, the new Township of Manitouwadge Official Plan, as adopted by By-law 2022-41. The approved new Township of Manitouwadge Official Plan outlines a comprehensive framework of new and revised policies to guide growth and development.
September 14, 2023 - October 29, 2023 (45 days) Closed
Last updated
Approval is granted to to add glass recycling operations to the facility’s operations, as well as changes to the quantities of waste received and the processed materials stored at the site.
The Ministry issued an Environmental Compliance Approval (ECA) for Kingfish Pumping Inc. for a hauled sewage waste disposal site. The ECA is for the storage lagoon of residential hauled sewage, located in Carleton Place, Ontario.
Permit to Take Water No. P-300-3096049917 was issued to Vandyk-Uptowns Limited on April 29, 2024, to renew Permit to Take Water No. P-300-3096049917 for construction dewatering purposes. Water will be taken from one well in the City of Brampton, Regional Municipality of Peel, Ontario for 3 years.
We approved an amendment to the Environmental Compliance Approval (a waste disposal site) No. A220249 issued to Safety-Kleen Canada Inc., for the addition of new waste types, waste processing activities and waste storage areas to the facility located at 25 Regan Road in Brampton, Ontario.
The Director suspended Condition 1.1 of the Environmental Compliance Approval issued to INEOS related to air emissions (the “air ECA”). The Director also amended the air ECA as benzene discharges from the facility were above acceptable levels, despite several previous provincial orders requiring the company to reduce benzene emissions
Instrument type:
Approval to amend a municipality’s official plan
ERO number
019-6135
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
May 30, 2023 - June 29, 2023 (30 days) Closed
Last updated
A decision was made on April 26, 2024 to approve, with modifications, Official Plan Amendment № 2, as adopted by By-law 2022-26. The amendment updates the official plan in accordance with section 26 of the Planning Act, to reflect the Township's goals and objectives, and to ensure the plan aligns with current provincial land-use policies.
The Permit to Take Water No. 8085-D4CLGS was issued to Hamilton Golf and Country Club on May 1, 2024, for 5 years for commercial purposes to renew the permit 6406-AXVKFA. Water will be taken from four wells, one ponds, and Ancaster Creek related to golf course irrigation activities, located in the City of Hamilton, Ontario.
September 12, 2023 - October 27, 2023 (45 days) Closed
Last updated
We have issued an Environmental Compliance Approval for a waste processing site approved to receive, transfer and process waste alkaline batteries in Thorold, Ontario.
Approval is granted for a new Environmental Compliance Approval for 2752985 Ontario Inc. for the on-site stormwater management works to service proposed industrial building development with associated parking and driveways, located at 246 Waydom Drive in Ayr, Ontario.