December 11, 2023 - January 10, 2024 (30 days) Closed
Last updated
This was for a Permit to Take Water for Cornwall Street and Railway Light and Power Company Limited under Permit No. P-300-9238755361 for the purpose of heat pump operation at 1001 Sydney Street, Cornwall, Ontario.
We have approved updates to the assessment reports and source protection plans for the Ausable Bayfield Maitland Valley Source Protection Region. Proceeding with these updates will ensure the assessment reports and source protection plans are current and in place to protect sources of drinking water for the region.
January 8, 2024 - February 22, 2024 (45 days) Closed
Last updated
Certificate of Property Use No. 3437-C5RNLH for 178 – 180 Queens Quay East, Toronto was issued to Rom-Grand Waterfront Ltd., as part of their development plans for the site.
January 12, 2024 - February 11, 2024 (30 days) Closed
Last updated
The Director of Exploration has made a decision on the exploration permit application PR-24-000002 to Explor Resources for early exploration activities
The decision is to issue the mineral exploration permit.
July 25, 2018 - September 8, 2018 (45 days) Closed
Last updated
The proponent has informed the ministry that they have decided to withdraw their Environmental Compliance Approval application for this proposal. Should the proponent wish to re-apply, the ministry will continue to ensure the protection of the health and safety of the environment and public in its technical review of the application.
An amendment to Environmental Compliance Approval (air & noise) No. 9683-8QEMM8, has been granted to R. W. Tomlinson Limited, operating a quarry, crushing plant, and a hot mix asphalt plant, located at 952 Moodie Drive in Nepean, Ontario.
February 9, 2023 - March 26, 2023 (45 days) Closed
Last updated
We have issued an Environmental Compliance Approval with Limited Operational Flexibility (air) to Bluewater Agromart Limited for a mixed fertilizer manufacturing facility, located in Ripley, Ontario.
The Director of Exploration has made a decision on the exploration permit application PR-24-000024 to Ashley Gold Corp. for early exploration activities.
The decision is to issue the mineral exploration permit.
February 24, 2021 - April 10, 2021 (45 days) Closed
Last updated
Approval was granted for a new Environmental Compliance Approval (air & noise) for Brantco Holdings Limited for the operation of a mobile crushing plant, equipped with one primary jaw crusher, one screening plant, two stackers and associated diesel engines.
This Permit to Take Water is being issued for operations associated with the Hardrock Project, for which public consultation on this alternative was previously conducted under an Individual Environmental Assessment (EA Reference No. 14175; File No. EA-02-10).
November 28, 2023 - December 28, 2023 (30 days) Closed
Last updated
Permit to Take Water No. 3457-D3DH8C was issued to 388015 Ontario Limited, operating as Lake St. George Golf Club on March 18, 2024, to renew Permit to Take Water No. 7022-CBYP8U for golf course irrigation purposes. Water will be taken from Lake St. George in the Town of Orillia, County of Simcoe, Ontario for 3 years.
January 4, 2024 - February 3, 2024 (30 days) Closed
Last updated
Permit to Take Water No. P-300-2258329193 was issued to Big Cedar Point Golf and Country Club Limited on March 19, 2024, to renew Permit to Take Water No. 8530-97KP9N for golf course irrigation purposes. Water will be taken from Lake Simcoe in the Town of Innisfil, County of Simcoe, Ontario for 10 years.
February 9, 2022 - March 29, 2022 (48 days) Closed
Last updated
The government is seeking input on creating an optional enhanced time-of-use electricity rate to encourage consumers to shift electricity use to low-demand periods, modelled after the OEB pricing pilot which included an ultra-low overnight price.
We are also seeking input on ways to address barriers to further enable electric vehicle adoption.
We are proposing to expand the boundary of Bigwind Lake Provincial Park, located approximately 20 kilometres east of Bracebridge. Expanding this park would provide long-term protection and enhanced opportunities for recreational activities, such as hiking and backcountry camping.
June 22, 2023 - September 4, 2023 (74 days) Closed
Last updated
We have decided to continue to the next stage of the management planning process for Bigwind Lake Provincial Park, which is the development of a preliminary management plan. A new management plan is required to create the first new full-service operating provincial park in 40 years at Bigwind Lake Provincial Park.
We issued an Environmental Compliance Approval to Greenflow Environmental Services Inc. to amend the environmental compliance approval for their existing subject waste transfer and processing site. This amendment allows the hand-sorting of pharmaceutical waste and the solidification of non-hazardous liquid industrial waste.