Decision summary

The 2024 Building Code made changes related to the requirements for sewage systems. The changes include updating an existing reference standard for septic tanks, clarifying the use of distribution piping in filter beds, and materials used in area bed mantle.

Decision details

  • The Ministry of Municipal Affairs and Housing (MMAH) has authority for onsite sewage systems, where the system is wholly contained on a lot or parcel of land, serves only one lot or parcel of land, and the design capacity is not greater than 10,000 L/day (e.g., smaller systems typically used for homes and cottages). 
  • Onsite sewage systems can be generally described as systems through which domestic wastewater (including showers, toilets, sinks, dishwashers, etc.) is treated and disposed. 
  • There are contaminants in wastewater that, if they enter drinking water, can cause serious health problems and negatively affect the environment.
  • In the Building Code, Part 8: Sewage Systems sets out the technical provisions for the design, construction, maintenance, and ongoing operations of onsite sewage systems. 
  • From October 25, 2022, to December 9, 2022, the Ministry posted 14 proposed changes to the Building Code that related to Part 8: Sewage Systems on Ontario’s Environmental Registry of Ontario (ERO).
  • All 14 proposals were submitted by members of Ontario’s onsite wastewater industry. The Ministry did not analyze or modify the 14 proposals before posting on the ERO. These proposals received significant comments from stakeholders and the industry.
  • The 2024 edition of Ontario’s Building Code included three of the 14 proposed Building Code changes, specifically related to septic tanks, the location of pipes in filter beds, and area bed mantles.
  1. Septic Tanks
Background
  • Wastewater flows through a plumbing system to a septic tank and then into the leaching bed. Bacterial action within a septic tank helps break down and separate solids in the wastewater. Septic tank wastewater is considered primary treatment.

Summary of Change 

  • The Building Code referenced CSA B66 “Prefabricated Septic Tanks and Sewage Holding Tanks” standard, 2010 edition. The change to the Building Code updated the reference standard from 2010 edition to the 2021 edition.
  • The 2021 edition of CSA B66 includes a mandatory requirement for safety screens (to protect against falling into a septic tank) with surface openings greater than 200 mm, for the protection of public health and safety.
  • The 2021 edition of CSA B66 also expands the materials list in which septic tanks can be manufactured (e.g., thermoset and thermoplastics).
  • A holding tanks – which are not connected to leaching beds – would also be required to meet 2021 edition of CSA B66.
  1. Filter Beds 
Background
  • A filter bed is type of leaching bed. It does not have trenches, but instead is one large bed, with several layers.
  • A filter bed is designed with pipes, stone (or sometimes chambers in lieu of stone), and special “filter sand” that allows for optimum distribution while treating the wastewater.
  • A filter bed often has a smaller footprint, making it ideal for small lots where separation distances to lakes, wells, and structures may be an issue.

Summary of Change 

  • The Building Code was changed to clarify the installation requirements for pipes in filter beds.
  • Filter beds require piping to be evenly spaced over the stone layer. However, the Building Code was unclear about the location of the pipe near the edge of the stone layer (e.g., set back or on the edge).
  • A change was made to clarify that the location of the pipe it is within 600 mm of the edge of the stone layer.
  1. Area Beds
Background
  • The Type A and B Dispersal Beds are types of leaching beds.
  • Type A Dispersal Bed uses an “open bottom” treatment unit that sits on top of the bed. 
  • A Type B Dispersal Bed uses a closed treatment unit that is located remote and apart from the distribution bed.

Summary of Change 

  • The Building Code was changed to clarify the design and construction requirements for Area Beds by distinguishing the types of soils used in the sand layer and the mantle.
  • New provisions now clarify that the sand layer and mantle maybe be permitted to be constructed of different materials. Type A and B Dispersal Beds require a sand layer, but now if the existing soils provide good drainage, then the 15 m mantle could be made of the existing soils, imported sand, or leaching bed fill.
  • The change could reduce the amount of soils (sand and/or leaching bed fill) required to be transported and, in turn, be a cost saving to owners.

Comments received

Through the registry

111

By email

0

By mail

0
View comments submitted through the registry

Effects of consultation

  • 14 proposals were submitted by members of Ontario’s onsite wastewater industry. MMAH did not analyze or modify the 14 proposals before posting on the ERO and received significant comments from stakeholders and the industry.
  • Having reviewed the comments, as well as hearing directly from key stakeholders (i.e., emails and meetings), it became clear that further discussions and additional consultations would be required with the sector. 
  • To assist MMAH with the consideration of the 14 proposals, a 17-member Technical Committee (which met twice in the Spring of 2023) was comprised of industry experts, and was established to provide additional input, feedback, and to further consult with the sector. The purpose of the Technical Committee was:
  1. to review the proposed changes,
  2. to review the comments submitted during public consultation, and 
  3. for the Technical Committee to share findings and provide feedback to MMAH.

The following summaries actions taken in respect of the 14 proposals.

Three proposals (1, 2, and 3 below) of the 14 proposals were included in the 2024 edition of the Building Code. 

  1. Septic Tanks 
  • The updated standard may slightly increase the cost of a septic tank, but it also increases safety. 
    • Most manufacturers are already complying with the updated standard. 
    • Comments received from consultation were supportive.
    • The Technical Committee was fully supportive. 
  1. Filter Beds 
  • The change created clarity and certainty, resulting in efficiencies in the design and review of these systems.
    • Those systems that use the existing soil would save the cost of importing sand or leaching bed fill.
    • A large majority Technical Committee support this proposal. The same support was indicated through the consultation. 
  1. Area Beds
  • There were issues raised during consultation that the proposal may eliminate the need for a fully-sized mantle, which could lead to sewage system failures. Failed systems can be hazardous to human health and the environment.
  • Several arguments and opinions were submitted in support of this proposal but no new information, testing, or research was included in the proposal. 
  • The proposal could reduce the amount of soils (sand and/or leaching bed fill) required to be transported and, in turn, be a cost saving to owners.
  • The manufacturers of Type A and B beds submitted this proposal but the request may be viewed by others in the industry as providing an advantage.
  • A slight majority of Technical Committee members supported the change.

Two (4 and 5 below) of the 14 proposals were developed into “Appendix Notes” and added to Building Code Compendium. While Appendix Notes are not regulation, they offer additional information (e.g., drawings, explanations, intent), which is helpful to the sector in the design and construction of onsite sewage systems. 

  1. Grey Water Systems - to allow for increased flexibility in the design of Class 2 greywater systems that would allow for trench-like designs.
  • There was some support for the proposal during the consultation. Concerns were raised about the lack of definitions for pit or trench in the Building Code, and the calculations used to determine the length of the trench for greywater systems.
  • The Technical Committee noted that some municipalities already permit the greywater systems to be designed as trenches.
  • The Technical Committee was unanimous in its support to develop an Appendix Note.
  1. Filter Beds - to align Building Code requirements for filter bed mantles with other leaching bed systems.
  • The Technical Committee explained that the intent of the proposal was not to include additional Code requirements, but instead clarify the existing requirements.
  • There was some support for the proposal received through the consultation.
  • A significant majority of the Technical Committee did not support the proposal as a regulation change, but instead recommended that an Appendix Note be developed to clarify this requirement. 

The remaining six of the 14 proposals were not included in the 2024 Building Code or the Appendix Notes to the Building Code.

  1. , 7., and 8. (Three similar proposals, one for each chamber of low-profile size) Chamber Systems - to allow for the use of three low-profile chambers sizes (i.e., LP 1, 2, & 3).
  • There was a mix of comments received from the consultation.
  • The Technical Committee also had a mix of comments, with approximately 50% support for the three LPs chambers.
  • There were unresolved concerns, including the reduction in the storage volume of wastewater, design requirements (e.g., vertical separation, coverage) and the calculation used appeared to be an alternative formular/method not in the Building Code.
  • The addition of three new and low-profile chamber types in the Code could add design flexibility, increasing options for consumers. 
  • The Technical Committee and the comments received during consultation noted the lack of supporting information for the LP chambers products and the lack of details about the LP chambers’ design and installation.

9.  Chamber Systems - to remove the requirement for a distribution pipe in a 

     chamber system 150 m and longer.

  • The purpose of the pipe to help distribute the effluent throughout the leaching bed, when the system is large (more than 150 m long) or when the sewage system requires pumping because it is above the ground or at a distance from the treatment units (e.g., primary, or tertiary).
  • If distribution pipes in chambers more than 150 m long were to be removed it would pose risks of system failure, human health, safety, and the environment.
  • Concerns were expressed about system failures (e.g., ponding, scouring of soils, pumping/dosing). 
  • The removal of distribution pipes in chamber systems could save consumers a negligible amount.
  • Concerns were expressed that the proposal had an unresolved issue that was linked to calculation and design.     
  • There was little support overall from the Technical Committee and during consultations for this proposal. 

10., 11., 12. and 13. (four interconnected proposals for the Combined Treatment and Dispersal Systems/Units) A new Leaching Bed Type - to add the requirements related to the design and construction of Combined Treatment and Dispersal Systems/Units, including provisions related to certification, sampling, and competency criteria into the Building Code.

  • During consultations and at the Technical Committee, issues were raised about the description of the proposed leaching bed and whether it is considered a “system” that preformed both treatment and disposal functions, or if it is a “unit” that only provides treatment, for which an extra disposal area would be required.
  • The validity of the four proposals came into question, as it appeared there was a need for further development, input, and agreement on the scope of the proposal.
  • The Technical Committee understood that the four proposals required major modifications.  
  • A significant majority of the Technical Committee did not support the four proposals, but instead recommended that the four proposals undergo further development for future consideration.

14. Horizontal Distances for Type A Beds - to modify the way Type A Bed horizontal clearance distances are measured from the open bottom treatment unit, where the level IV treated wastewater enters the leaching bed.

  • The manufacturers of these systems stated that the design and construction of Type A Beds would be smaller (possibly cheaper) and fit on difficult lots. 
  • Several opinions were submitted in support of this proposal, but no new information, testing, or research was presented to modify existing minimum health and safety requirements.
  • Risks to health, safety, environment were expressed.

A narrow majority of Technical Committee members supported the change.

Supporting materials

View materials in person

Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.

Get in touch with the office listed below to find out if materials are available.

Building and Development Branch
Address

12th Flr, 777 Bay St,
Toronto, ON
M7A 2J3
Canada

Office phone number

Connect with us

Contact

Share

Email

Facebook

X

Sign up for notifications

We will send you email notifications with any updates related to this consultation. You can change your notification preferences anytime by visiting settings in your profile page.

Follow this notice

Original proposal

ERO number
019-6211
Notice type
Regulation
Act
Building Code Act, 1992, S.O. 1992, c. 23
Posted by
Ministry of Municipal Affairs and Housing
Proposal posted

Comment period

October 25, 2022 - December 9, 2022 (45 days)

Proposal details

Ontario’s Building Code is a regulation under the Building Code Act, 1992 which sets out minimum administrative and technical requirements for new construction, renovation, and change of use of buildings.

The Ministry of Municipal Affairs and Housing has been actively working on the development of the next edition of the Building Code since 2021.

The third and final phase of consultation focuses mainly on remaining Ontario-specific proposals and issues identified through the first two phases of consultation.

Due to their potential relevance to the environment, a proposal related to energy efficiency and proposed Part 8 changes on sewage systems are being posted separately from other Phase 3 proposals (see attached List of Proposed Changes to Sewage Systems and Energy Efficiency).

The Phase 3 consultation consists of engagement and discussion in November/December 2022, and three simultaneous online postings. In addition to this current posting on proposed sewage system and energy efficiency changes, the other two postings are on the Regulatory Registry of Ontario on:

  1. General Proposed Changes for the Next Edition of Ontario’s Building Code
  2. Building Code Changes to Support More Homes Built Faster: Ontario’s Housing Supply Action Plan 2022-23

The ministry will continue to carefully review and analyze the feedback collected from all three phases of consultation. This information will inform the drafting of the next edition of Ontario’s Building Code.

Please submit comments on any of the proposed changes by:

  1. using the link provided within the attached list of proposals, or
  2. submitting an email directly to buildingcode.consultation@ontario.ca with the Sentence(s) or Article number(s) as the subject line.

This posting is open for 45 days for feedback. A bulk comment form is also available and is attached below.

Analysis of Regulatory Impact

Costs: There are no new administrative costs anticipated for regulated entities.

Benefits: The proposed changes would update requirements and increase harmonization between Ontario’s Building Code and National Construction Codes.

Supporting materials

View materials in person

Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.

Get in touch with the office listed below to find out if materials are available.

Comment

Commenting is now closed.

This consultation was open from October 25, 2022
to December 9, 2022

Connect with us

Contact

buildingcode.consultation@ontario.ca